WELCOME TO THE PEPPERPOT

NEWS – 27/04/16

On Monday 21st members of the Sedbergh Parish Council, Cumbria Wildlife Trust, Sedbergh and District History Society and the Pepperpot Music Group were invited to...
Read More

WEEK 15

As Sedbergh enjoys half term the final touches are applied inside Pepperpot. Thank you to Nicola Hetherington for the beautiful photograph.

WEEK 14

The scaffolding is down and the building revealed as work continues inside.

WEEK 13

Work progresses on the Key Stage 2 Education Pack – get in touch if you’d like to visit with your class!

WEEK 12

This week the roof tiling has been completed as Sedbergh enjoys beautiful autumn weather.

WEEK 11

The first skin roof is in and the waterproof membrane in place. We’ll be ready for visitors soon.

WEEK 10

Work continues to make the building watertight

WEEK 9

The spell of good weather has allowed for the erecting of the first floor and start of work on the roof.

WEEK 8

Joinery work offsite is complete and the windows are ready to be fitted. Thanks to our builders for the good progress!

WEEK 7

Sedbergh enjoys some late summer sun. Offsite carpentry work on the first floor is well underway.

WEEK 6

Off-site the Joiners have begun work on the windows and frames for the first floor.

WEEK 5

All the coping stones are in place and the blockwork is finished.

WEEK 4

During Week 4 the carving of stone lintels offsite has progressed. Onsite preparations have been made for the first floor to go up. The tiles...
Read More

WEEK 3

Week 3 of the build has seen the block work on the ground floor finished. Off site work creating the stone cills, coping and lintels...
Read More

WEEK 2

Week 2 of the build: a new concrete floor has been poured, the existing stone work has been stabilised with mortar and the new ground...
Read More

WEEK 1

Work began at Pepperpot on 13th July. In the first week workmen cleared rubble from the ground floor of Pepperpot.